作者机构:Knoxville Power Company Alcoa Tennessee United States
出 版 物:《Transactions of the American Institute of Electrical Engineers》 (Trans. Am. Inst. Electr. Eng.)
年 卷 期:1931年第50卷第1期
页 面:284-287页
主 题:Lightning Poles and towers Power transmission lines Cables Insulation Steel Distributed parameter circuits Crystallization
摘 要:The cooperative lightning laboratories near Alcoa, Tenn., have been in operation since July, 1928. This paper outlines the purpose of the installation and describes the transmission line on which the studies are being conducted. A background is provided for a more complete appreciation of the technical data which appear from time to time. Conclusions drawn from an operating viewpoint are presented. © 1931. By A. I. E. E.